Construction Cash Flow Forecasting
See cash gaps in your building business weeks before they happen, while there's still time to act
- 20+ years connecting business systems
- Works with the accounting, job and CRM systems you already use
- Fixed quote after a free chat

Profit Isn't Cash
You can be profitable on paper and still scramble to make payroll. Clients take weeks to pay progress claims, subcontractors want paying sooner, suppliers want money before they deliver, and retention money sits out of reach for months.
Every month you check the bank balance and wonder if there's enough. Supplier payments get delayed to cover wages, new projects get put off because you're not sure you can fund the early costs, and decisions are made on gut feel.
The reality: Plenty of builders with full order books still go under, because the cash arrives too late to cover what is going out. Construction regularly tops ASIC's company insolvency statistics, and cash flow timing is a common thread.
Could You Answer These Questions Today?
Illustration: A Builder With 5 Active Projects
Contract Value
$8.7M
Claims Outstanding
$2.3M
Retention Held
$385K
Subbies Due (30d)
$1.1M
Wages (30d)
$280K
Materials On Order
$420K
Questions the forecast answers:
- When will the $2.3M in outstanding claims actually turn into cash?
- Can we cover $1.1M in subbie payments next month if two claims are late?
- Which project is using cash fastest compared with what it has claimed?
- What is the lowest our bank balance will get in the next 8 weeks?
- Should we delay the new project start or arrange bridging finance?
Without a forecast, answering these takes hours in a spreadsheet. With one, the answers are on a dashboard updated daily from your accounting and construction data.
A 13-Week Forecast Driven by Your Claim Schedule
A construction cash flow forecast built from the accounts runs a month behind, because the accounts only know what has already been invoiced and paid. Next month's claims aren't in there yet, a subcontract signed last week won't show until its first bill, and retentions sit as a balance with no date.
So we build the forecast from the jobs instead, week by week for the next 13 weeks, and refresh it every week from your job system, claims and accounts. Each job contributes:
The claim schedule
When each progress claim goes in, by job, and roughly how much, from the contract and the job program. This drives almost all of the cash coming in.
When each claim is actually paid
The payment due date under the contract and your state’s security of payment rules, then adjusted for how that client really pays. A client who always pays on the last allowed day, or a week late, is forecast that way.
Retentions
Retention your clients hold comes back at practical completion and the end of the defects period, so those dates go in as receipts. Retention you hold from subcontractors goes back out on the same kind of dates.
Committed costs
Every signed subcontract and purchase order, the amount still to be billed, and the week the payment falls due under your terms and your pay-run days.
Cost to complete
What hasn’t been ordered yet (labour, materials, later trades), spread over each job’s remaining weeks using WIP and the program.
Wages, overheads and tax
Pay runs, super, rent, insurance, loan repayments and BAS, on the dates they actually fall.
An example forecast
Illustration only: a made-up builder with five active jobs, figures in thousands of dollars, opening bank balance 300.
| Week | Claims paid in | Retention back | Subbies and suppliers | Wages | Overheads and tax | Closing balance |
|---|---|---|---|---|---|---|
| 1 | – | – | 80 | 45 | 15 | 160 |
| 2 | 640 | – | 300 | 45 | 15 | 440 |
| 3 | – | – | 60 | 45 | 120 | 215 |
| 4 | 520 | – | 330 | 45 | 15 | 345 |
| 5 | 310 | – | 60 | 45 | 15 | 535 |
| 6 | – | – | 380 | 45 | 15 | 95 |
| 7 | – | – | 20 | 45 | 15 | 15 |
| 8 | 590 | – | 300 | 45 | 15 | 245 |
| 9 | 280 | 95 | 60 | 45 | 15 | 500 |
| 10 | – | – | 290 | 45 | 15 | 150 |
| 11 | 300 | – | 60 | 45 | 15 | 330 |
| 12 | 590 | – | 300 | 45 | 15 | 560 |
| 13 | – | – | 60 | 45 | 15 | 440 |
The bank balance looks fine in week 5. The forecast shows why it won't stay that way: a large subcontractor run lands in week 6, and the next big claim (for Job B) is due on the last day of week 7, from a client who usually pays a few days late. Week 7 is the low point. If that payment slips into week 9, week 8 goes negative.
Seen in week 1, that gives you six weeks to act: get Job B's claim in early, check the payment schedule arrives on time, move a materials order back a week, agree the timing of the week 6 subcontractor run, or talk to the bank before you need to. Seen in week 6, the only option is a phone call you'd rather not make.
The week 3 tax payment and the week 9 retention release are there because they were entered with a date, not left as balances. That is most of what separates this from a forecast rebuilt from the accounts.
How Payment Schedule Deadlines Feed the Forecast
Under each state's Security of Payment Act, a payment claim starts two clocks: the time the other party has to give a payment schedule, and the date payment is due. Both are set by the contract within limits in the Act, and the limits differ between Queensland, New South Wales and Victoria. The forecast uses them like this:
- Claim date. From your claim schedule, which follows the contract and the program.
- Payment schedule deadline. Calculated in business days from the claim. When a schedule arrives for less than you claimed, the forecast drops to the scheduled amount and the difference is flagged for follow-up. When no schedule arrives by the deadline, that is flagged too, because it changes your position under the Act.
- Payment due date. The date the cash should land, which is where the claim first appears in the forecast.
- Actual pay lag. Each client's payment history moves the receipt to when they really pay. The gap between due and actual is worth watching on its own.
The same clocks run the other way on claims your subcontractors send you: your payment schedule deadline and your payment date become dated outgoings. Missing a payment schedule deadline on a subcontractor's claim can leave you owing the full amount claimed, so the forecast and the claims register share the same dates. Business-day counting also stretches deadlines over the Christmas break, which matters in a forecast that spans December and January.
The rules, deadlines and recent Victorian changes are set out in our guide to progress claims, payment schedules and retention tracking across Qld, NSW and Victoria. For your own contracts, check with a construction lawyer.
When a spreadsheet is enough
With a handful of jobs and one person who updates the claim schedule and commitments every week, a well-built spreadsheet does this job. Our article on building a 13-week forecast from WIP and your claim schedule shows the structure. It is worth automating when there are many jobs, the inputs come from several people and systems, or the forecast is only rebuilt at month end because nobody has time to keep it current.
Seven Cash Flow Killers in Construction
Common cash flow problems and how forecasting helps with each one
Numbers a Month Behind
Late Progress Claims
Slow Client Payments
Front-Loaded Costs
Retention Building Up
Variation Delays
Seasonal Slowdowns
Where Forecast Data Comes From
We connect to the systems you already use, so nobody has to enter anything new
Xero
Invoices, bills, bank balances, payment history, aged receivables
MYOB
The same accounting data as Xero, including how each client pays
Procore
Committed costs, budget forecasts, variations and progress claim schedules
Buildxact
Project budgets, purchase orders and progress claim amounts
Simpro
Job costs, quotes, purchase orders and work in progress
Bank Feeds
Your actual bank balance and transactions, to check against the forecast
Frequently Asked Questions
See Cash Gaps Before They Happen
Start with a free initial chat about how you track cash flow today and what you need to see coming, so you know, rather than guess, whether you can cover next month's bills.
Part of our guide: Construction Finance Systems Guide
See also
Articles on this topic
- From Progress Claim to Payment Certificate to Retention: The Paperwork Between Your Systems
- From Variation to Progress Claim Without Retyping: One Workflow in a Typical Building Business
- Why Your Construction Cash Flow Forecast Is a Month Behind (and How to Build One From WIP and Your Claim Schedule)
- Progress Claims, Payment Schedules and Retention Tracking Across Qld, NSW and Victoria