Preventive Maintenance Schedule: Template, Example and Work Order Process

26 November 2026 Aaron Chambers Business Strategy

It is Wednesday afternoon and the site fitter finds a hydraulic hose about to fail on a loader that should have been serviced three weeks ago. The service was on someone's whiteboard, but nobody moved it into an actual schedule. Now the machine is down, the hose is not in stock, and the job it was working on is a day behind.

A preventive maintenance schedule is a plan that lists every asset, the maintenance tasks each one needs, how often each task is due, who does the work, and what parts are required. Instead of waiting for something to break and then reacting, you service equipment at set intervals so breakdowns happen less often and cost less when they do.

This post covers what goes in a schedule, the difference between time-based and usage-based maintenance, a worked example for a few plant items, a template you can copy, and the work order process from request to close-out.

Time-based vs usage-based maintenance

There are two ways to decide when a task is due.

Time-based maintenance runs on a calendar. You service the item every week, month, quarter or year regardless of how much it has been used. This suits fixed plant, building services, fire equipment and anything subject to a regulatory inspection cycle. The advantage is simplicity. The risk is that a machine running double shifts gets the same service interval as one sitting idle.

Usage-based maintenance triggers on a meter reading. You service the item every 500 engine hours, every 10,000 kilometres, or every 50,000 cycles. This suits mobile plant, vehicles, compressors and production equipment where wear depends on how hard the machine works. It is more accurate but needs someone to record meter readings regularly.

Most businesses use both. A truck might get a minor service every 10,000 km (usage) and a full inspection every 12 months (time), whichever comes first.

| Trigger | Best for | Example | What you need to track | |---|---|---|---| | Time-based (calendar) | Fixed plant, building services, fire systems, regulatory inspections | Quarterly grease on conveyor bearings | Last done date, next due date | | Usage-based (meter) | Vehicles, mobile plant, compressors, production machines | Engine oil every 500 hours | Current meter reading, reading at last service, trigger reading | | Whichever comes first | Trucks, loaders, generators | Minor service at 10,000 km or 6 months | Both a date and a meter reading |

What columns belong in a preventive maintenance schedule

The schedule is a table. Each row is one task on one asset. The columns capture enough to tell the team what to do, when, with what parts, and who is responsible.

| Column | What it records | |---|---| | Asset ID | A unique reference (e.g. PMP-012 or the fleet number) | | Asset name | Plain description: "Komatsu PC200 Excavator" or "Warehouse Compressor 1" | | Location or site | Where the asset sits: pit, workshop, warehouse, north site | | Task | What the service involves: "Replace hydraulic oil and filters", "Grease bearings", "Check belt tension and alignment" | | Frequency | How often: weekly, monthly, every 500 hours, every 10,000 km | | Trigger type | Time, usage, or whichever comes first | | Last done | Date (and meter reading if usage-based) of the last completed service | | Next due | Date (and meter reading) the next service falls due | | Estimated duration | How long the task takes (e.g. 2 hours) | | Parts required | Filters, belts, oil type and quantity, gaskets | | Assigned to | The fitter, contractor or team responsible | | Priority | Critical, high, medium, low | | Reference | The OEM manual section, the Australian Standard, or the site procedure | | Status | Scheduled, overdue, in progress, complete |

Worked example: a small fleet and fixed plant

This is an illustrative example with typical intervals, not a service specification. Your manufacturer's manual and your maintenance team set the actual intervals and tasks.

For example, a mid-sized quarry operation runs three items alongside its main plant.

Asset 1: Komatsu PC200 Excavator (fleet number EX-03)

| Field | Value | |---|---| | Asset ID | EX-03 | | Location | Main pit | | Task 1 | Engine oil and filter change | | Frequency | Every 500 engine hours | | Trigger | Usage-based | | Last done | 12 Nov 2026 at 4,520 hrs | | Next due | At 5,020 hrs (for example, mid-January if running 40 hrs/week) | | Parts | 18L 15W-40 oil, 1 x oil filter, 1 x fuel filter | | Assigned to | Site fitter | | Task 2 | Hydraulic system inspection and fluid top-up | | Frequency | Every 1,000 engine hours | | Last done | 12 Nov 2026 at 4,520 hrs | | Next due | At 5,520 hrs | | Parts | Hydraulic fluid as needed, inspection checklist | | Assigned to | Site fitter |

Asset 2: Workshop air compressor (COMP-01)

| Field | Value | |---|---| | Asset ID | COMP-01 | | Location | Workshop | | Task | Drain condensate, check belt tension, inspect inlet filter | | Frequency | Weekly (time-based) | | Last done | 22 Nov 2026 | | Next due | 29 Nov 2026 | | Parts | Replacement inlet filter (keep one spare) | | Assigned to | Workshop leading hand |

Asset 3: Overhead crane (CR-01)

| Field | Value | |---|---| | Asset ID | CR-01 | | Location | Fabrication bay | | Task | Annual inspection and load test per AS 2550 | | Frequency | Annually (time-based) plus pre-use daily checks | | Last done | 15 Mar 2026 | | Next due | 15 Mar 2027 | | Parts | None for the inspection; defects raised as separate work orders | | Assigned to | External inspector (booked by maintenance coordinator) |

Template you can copy

Below is a preventive maintenance schedule template. Copy it into a spreadsheet or use it as the starting point for a simple database. Add one row for each task on each asset.

| Asset ID | Asset name | Location | Task | Frequency | Trigger | Last done (date) | Last done (meter) | Next due (date) | Next due (meter) | Est. duration | Parts required | Assigned to | Priority | Reference | Status | |---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---| | EX-03 | Komatsu PC200 Excavator | Main pit | Engine oil and filter change | 500 hrs | Usage | 12 Nov 2026 | 4,520 hrs | - | 5,020 hrs | 2 hrs | 18L oil, oil filter, fuel filter | Site fitter | High | OEM manual Ch. 7 | Scheduled | | EX-03 | Komatsu PC200 Excavator | Main pit | Hydraulic inspection and top-up | 1,000 hrs | Usage | 12 Nov 2026 | 4,520 hrs | - | 5,520 hrs | 1 hr | Hydraulic fluid | Site fitter | High | OEM manual Ch. 9 | Scheduled | | COMP-01 | Workshop air compressor | Workshop | Drain, belt check, inlet filter | Weekly | Time | 22 Nov 2026 | - | 29 Nov 2026 | - | 30 min | Inlet filter (spare) | Workshop leading hand | Medium | OEM manual | Scheduled | | CR-01 | Overhead crane | Fab bay | Annual inspection and load test | Annual | Time | 15 Mar 2026 | - | 15 Mar 2027 | - | 4 hrs | - | External inspector | Critical | AS 2550 | Scheduled |

The work order process: from request to close-out

A maintenance schedule tells you what is due. A work order is the document that makes it happen. Here is the process from start to finish.

Step 1: Work order raised. The schedule flags a task as due (or a breakdown happens and someone raises a reactive request). A work order is created with the asset, the task description, the priority, and the parts needed.

Step 2: Planning. The maintenance coordinator checks parts are in stock or orders them. If a part has a lead time, the work order waits. The coordinator assigns a fitter and a date.

Step 3: The work is done. The fitter completes the task, records what was done, notes any defects found, and logs the meter reading and date. If extra work is needed, a new work order is raised for it.

Step 4: Parts and costs recorded. The parts used are booked against the work order, and the fitter's time is recorded. This is where the cost of maintaining that asset gets captured.

Step 5: Close-out and sign-off. The supervisor or coordinator reviews the completed work order, confirms the work was done, and closes it. The schedule updates the "last done" and "next due" fields.

Step 6: History. The closed work order becomes part of the asset's maintenance history. When someone asks how much the excavator cost to maintain last year, the answer comes from these records.

| Step | Who | What happens | Record created | |---|---|---|---| | 1. Raise | Schedule or operator | Work order created with asset, task, priority, parts | Work order (open) | | 2. Plan | Maintenance coordinator | Parts checked or ordered, fitter and date assigned | Work order updated | | 3. Do | Fitter or contractor | Task completed, defects noted, meter reading logged | Completion notes | | 4. Cost | Fitter or stores | Parts issued, labour hours recorded against the work order | Parts issue, timesheet | | 5. Close | Supervisor or coordinator | Work reviewed, work order closed, schedule updated | Work order (closed) | | 6. History | System or filing | Closed work order stored as asset history | Maintenance log |

Where the process breaks

The schedule and the work order process look simple on paper. In practice, three things cause most of the trouble.

Parts not ordered in time. A service comes due, the fitter goes to the storeroom, and the filter is not there. The work order sits open, the machine runs past its service interval, and somebody scribbles "awaiting parts" on a clipboard. If the parts list on the schedule is not linked to purchasing or a minimum stock level, this repeats every month.

Costs not reaching the asset or the job. The fitter uses three litres of hydraulic oil and two hours of labour, but the storeroom does not issue the oil against the work order and the timesheet goes to payroll without a job or asset number. At the end of the quarter, the maintenance manager cannot tell the operations manager what each machine cost to maintain. The numbers sit in separate systems and nobody joins them up. This is information that stops before it is needed. If you also track those assets for accounting purposes, the same problem shows up in the fixed asset register when book values and physical condition tell different stories.

Records on paper or in someone's head. The daily pre-start check gets ticked on a printed form. The form goes in a folder in the site office. When the insurer or regulator asks for the history of a particular machine, somebody has to dig through ring binders. If the person who kept the records has left, the history leaves with them. Fire contractors and facility managers face the same paper trail problem with AS 1851 inspection records.

When maintenance schedules, work orders, parts, timesheets and costs all live in separate places, the picture is always incomplete. The maintenance manager has the schedule in a spreadsheet, the parts are tracked in the accounting system, the timesheets go through payroll, and the work orders are on paper or in a different app. Connecting those records so the schedule drives purchasing, costs land on the right asset, and history is in one place is a systems integration problem.

Frequently asked questions

What is the difference between preventive and predictive maintenance?

Preventive maintenance follows a fixed schedule: service the pump every 500 hours or every quarter, regardless of condition. Predictive maintenance uses live data (vibration sensors, oil analysis, thermal imaging) to service equipment only when the data shows it needs it. Most Australian businesses outside heavy industry start with preventive maintenance because it needs less equipment and is simpler to run. Good maintenance records also feed into production reporting and OEE, because unplanned downtime is one of the biggest drags on equipment effectiveness.

How do I decide the right service interval for an asset?

Start with the manufacturer's manual. It will specify intervals for oil, filters, belts and inspections. Adjust based on your operating conditions. A loader in a dusty quarry needs shorter filter intervals than the same machine on a paved yard. Your maintenance team and the OEM dealer are the best sources for adjusting intervals. Never guess figures.

Can I run a preventive maintenance schedule in a spreadsheet?

Yes, and many businesses do. A spreadsheet works when you have a small number of assets and one person managing the schedule. It stops working when you have dozens of assets, multiple sites, or several people raising and closing work orders. The spreadsheet cannot send reminders, link to parts stock, or automatically capture costs. At that point a maintenance management system (sometimes called a CMMS) earns its keep.

What is a CMMS?

A computerised maintenance management system (CMMS) is software that holds your asset register, maintenance schedule, work orders, parts inventory, and maintenance history in one place. It automates reminders, tracks costs by asset, and produces reports. Some run standalone. Others connect to your accounting or ERP system so parts purchasing and cost reporting flow through without re-keying.

How do I make sure maintenance costs end up on the right asset in my accounts?

The work order needs a field for the asset number, and that number needs to match the asset register in your accounting system. When a part is issued from stores or a fitter logs time, both should reference the work order. If your maintenance system and your accounting system do not talk to each other, someone has to retype those entries, and that is where the numbers go wrong.

If you are dealing with disconnected maintenance records, parts that never get ordered in time, or costs that never reach the right asset in your accounts, book a free initial chat and we will walk through what connecting your systems would involve.